Every system our crews delivered on this contract, item by item.

Water system

05
  • Temporary water main bypass
  • 6,000 linear feet of 6" to 16" water main
  • 3,000 linear feet of water services with removal of lead
  • 45 each new gate valves
  • 10 each new hydrants

Sewer/Drain system

03
  • Temporary sewer main bypass
  • 14,000 linear feet of 6" to 48" pipe
  • 120 each new 4' to 8' diameter manholes/catch basins

Rock Excavation

01
  • Removal, handling, transportation and disposal of 1,000 cubic yards of rock

Hot mix asphalt paving

01
  • 17,800 square yards of temporary pavement patching