Skip to content
All Projects
MassachusettsCompletedC08 / 18

Lexington

MWRA Contract 6522, Lexington

Massachusetts Water Resources Authority

Client: Massachusetts Water Resources Authority

Project Details

Every system our crews delivered on this contract, item by item.

Water System

04
  • Installing 5,200 LF of 24-inch DI watermain
  • Replacing 3,600 LF of 8-inch watermain for the town of Lexington
  • Replacing 5,100 LF of 16-inch watermain for town of Lexington
  • Transfer town of Lexington water services from existing 8-inch watermain to their new 16-inch watermain

Sewer System

01
  • Installing valves, precast valve vaults, air valves, blow-off assemblies, manholes

Other Projects

Planning A Similar Project?

Send our team your plans or RFP. We're glad to review scope and confirm fit before you finalize your team.

Get In Touch